1970 Chevelle Rear Axle Identification

[ 1964 ] | [ 1965 ] | [ 1966 ] | [ 1967 ] | [ 1968 ] | [ 1969 ] | [ 1970 ] | [ 1971 ] | [ 1972 ]

The rear axle identification code consists of a three letter prefix indicating the gear ratio, four digits indicating the assembly date as month/day, and a single letter suffix indicating the manufacturing location. The identification code should be stamped on the bottom or font of right axle tube either adjacent to the carrier housing or about 8" - 10" inboard from the backing plates. The particular engine RPO code is listed in parentheses as found on build sheets.

Example: CGI0629B decodes to CGI ~ 3.36:1 Positraction, 0629 ~ Month [June] and Day [29], B ~ Buffalo (G=Chevrolet Gear & Axle, W=Warren, K=McKinnon Industries). If a "1" or "2" exists, it indicates the plant shift number. See bottom of page for photo examples.

Casting Numbers:
12-Bolt Casting #3969278 - very early 1970s have been reported with #3959038 units.
10-Bolt Casting #3969277

The casting numbers/letters on rear end housings may have either a prefix or suffix of "N" or "NF" and no reason has been found yet why they may have one or the other. Codes below are for Chevelle & Monte Carlo.

Prefix Axle Ratio
CCA 3.08:1 ~ 10-bolt (L14/307 & L22/250)*
CCB 3.36:1 ~ 10-bolt
CCD 3.07:1 ~ 12-bolt Positraction
CCE 3.08:1 ~ 10-bolt Positraction
CCF 3.31:1 ~ 12-bolt Positraction (L34/402 & L48/350-4)*
CCG 3.36:1 ~ 10-bolt Positraction
CCH 2.73:1 ~ 12-bolt Positraction (L48/350-4)*
CCL 2.56:1
CCM 2.56:1 ~ Positraction
CCN 2.56:1
CCO 2.56:1 ~ Positraction (El Camino L34/396)*
CCP 2.73:1 ~ 10-bolt (L14/307)*
CCW 3.31:1 ~ 12-bolt (L34/402 & LS3/402 M.C.)*
CCX 3.07:1 ~ 12-bolt
CGA 2.56:1 ~ 10-bolt (L65/350-2)*
CGB 2.56:1 ~ 10-bolt Heavy Duty Positraction (L65/350-2)*
CGC 2.73:1 ~ Heavy Duty
CGD 2.73:1 ~ Heavy Duty Positraction
CGE 3.08:1 ~ 10-bolt Heavy Duty
CGF 3.08:1 ~ 10-bolt Heavy Duty Positraction
CGG 3.36:1 ~ 10-bolt Heavy Duty
CGI 3.36:1 ~ 10-bolt Heavy Duty Positraction
CKC 2.73:1 ~ Positraction
CKD 2.73:1 ~ 12-bolt (L48/350-4 & LS3/402)*
CKF 3.55:1 ~ 12-bolt Positraction (L78)*
CKJ 3.55:1 ~ 12-bolt (L78/402)*
CKK 4.10:1 ~ 12-bolt Positraction (L78/402)*
CRJ 2.56:1
CRK 2.56:1 ~ 12-bolt Positraction (Monte Carlo LS5/454)*
CRL 3.07:1 ~ 12-bolt
CRM 3.07:1 ~ 12-bolt
CRU 3.31:1 ~ 12-bolt (LS5/454 & LS6/454)*
CRV 3.31:1 ~ 12-bolt Positraction (LS5/454 & LS6/454)*
CRW 4.10:1 ~ 12-bolt Heavy Duty (LS6/454)*


Positraction 4.10:1 ring gear

Assembly Month - 1st and 2nd numbers
Number Month Number Month
01 January 02 February
03 March 04 April
05 May 06 June
07 July 08 August
09 September 10 October
11 November 12 December

Assembly Day - 3rd and 4th numbers
01...31

Rear Axle Assembly Plant - 5th letter

Code Assembly Plant
B Buffalo ~  New York
G Chevrolet Gear & Axle
W Warren ~  Michigan
K McKinnon Industries


CCF ~ Positraction 3.31:1 - August 21, Buffalo


CKF ~ Positraction 3.55:1 ~ October 7, Buffalo


CCW ~ 3.31:1 - September 18, Buffalo


CCP ~ 2.73:1 - October 1, Warren, MI.


CRU ~ 3.31:1 - October 20, Buffalo, 1st shift
(Suspect stamping as the letter "C" is not consistent with others of this year)


CCF ~ Positraction 3.31:1 - November 6, Buffalo, 1st shift


CCF ~ Positraction 3.31:1 - November 10, McKinnon ~ Courtesy Dane Belden


CCF ~ Positraction 3.31:1 - November 20, Buffalo, 1st shift


CRV ~ Positraction 3.31:1 - November 26, Buffalo, 1st shift


CRV ~ Positraction 3.31:1 - December 05, Buffalo, 2nd shift


CRV ~ Positraction 3.31:1 - December 08, Buffalo, 2nd shift


CRV ~ Positraction 3.31:1 - December 22, Buffalo, 1st shift


CCW ~ 3.31:1 - January 9, Buffalo, 2nd shift


CRW ~ Positraction 4.10:1 - February 12, Buffalo, 1st shift
(Suspect stamping as the letter "C" is not consistent with others of this year)


CCW ~ 3.31:1 - February 16, Buffalo, 2nd shift


CCH ~ Positraction 2.73:1 - February 18, Buffalo, 1st shift


CCW ~ 3.31:1 - February 27, Buffalo, 1st shift


CKD ~ 2.73:1 - March 20, Buffalo, 1st shift


CCF ~ Positraction 3.31:1 - March 25, Buffalo, 1st shift


CCF ~ Positraction 3.31:1 - April 8, Buffalo, 2nd shift


CRV ~ Positraction 3.31:1 - April 10, Buffalo, 2nd shift


CKD ~ 2.73:1 - April 15, Buffalo, 2nd shift


CCF ~ Positraction 3.31:1 - May 21, Buffalo, 1st shift


CRW ~ Positraction 4.10:1 ~ May 27, Buffalo, 2nd shift


CGA ~ 2.56:1 - June 02, Buffalo, 1st shift


CRW ~ Positraction 4.10:1 - June 03, Buffalo, 2nd shift


CF ~ Positraction 3.31:1 - June 27, Buffalo (Appears someone was lazy and only stamped this CF instead of CCF)

Casting Date Examples


Casting date example of I 8 9 for September 8, 1969


Casting date example of J 10 9 for October 10, 1969


Casting date example of K 10 9 for November 10, 1969


B 27 0 for February 27, 1970


C 5 0 for March 5, 1970


Casting date example of E 8 0 for May 8, 1970


Casting date example of E 11 0 for May 11, 1970


Casting date example of F 24 0 for June 24, 1970


Casting date example of G 28 0 for July 28, 1970

Casting Number Examples




1970-1972 ~ Variations of casting number 3969278

* Engine RPO code and size following the rear axle ratio are taken from build sheets and/or Protect-O-Plates and may not reflect the only engines the rear axle codes came with. Where there are no RPO/engine information following the rear axle code only means I do not have build sheets and/or Protect-O-Plates to verify them.